According Judge Robert G. Holt, “OSM violated NEPA [National Environmental Protection Act] by not preparing a supplemental draft EIS [Environmental Impact Statement] when Peabody changed the proposed action. As a result, the Final EIS did not consider a reasonable range of alternatives to the new proposed action, described the wrong environmental baseline, and did not achieve the informed decision-making and meaningful public comment required by NEPA. Because of the defective Final EIS, OSM’s decision to issue a revised permit to Peabody must be vacated and remanded to OSM for further action.”

 